THE PLAN - WATER

From the lampi to the tap, without pretending the middle does not exist.

The source is part of the story. Potable-water claims will only follow actual laboratory data and a commissioned treatment chain.

01

Muuraislampi

Source water.

→
02

Pump

Direct supply to the site.

→
03

Lab + treatment

Decide from measured water quality.

→
04

Guest tap

Only after commissioning.

Done
W01

Muuraislampi as the intended water source

The lampi is the intended source because drilling a well is expensive; potable use remains conditional on laboratory results and suitable treatment.

W02

Automatic pumped supply from the lampi

Replace manual water handling with a direct pump and supply route to the containers.

W03

Laboratory water analysis

Test the lampi water before deciding the potable-water treatment chain.

Waiting
W04

Treatment decision from lab results

The final potable-water design depends on what the laboratory results actually show.

Depends on W03
Planned
W05

RO / UV drinking-water treatment

If the laboratory results support it, install the intended reverse-osmosis and UV treatment system.

Depends on W04
Planned
W06

Commission guest water system

Verify the complete water path and write the guest-facing operating guidance.

Depends on W05

THE BOUNDARY

Water provenance can be a strength. Unsafe water cannot.

The interesting part is understanding where the water comes from. The safety requirement stays boring, tested and non-negotiable.